Job Costing Tracker

Track estimated vs actual costs for electrical projects with real-time profitability analysis and variance reporting.

Actual vs Estimate — Phase View

Material, labor, and margin variance by phase. Estimates pull from the BOM and labor engine; actuals pull from field time tracking and purchases. Click any actual to edit. Example: Drywall garage fire-separation.

Overall Job Margin
29.6%-4.8 pts
Estimated 34.4% · Bid $6,000
Est Cost
$3,939
Actual Cost
$4,225
Variance
+$286
100% of cost lines tracked107% of est. spent
Labor 8% over — check Hang phase.
Margin down 4.8 pts vs estimate (now 29.6%).
2.0 labor hrs not mapped to a phase — review the Unaccounted row.

Total Cost

Estimated
$3,939
Actual
$4,225
+$286 (+7.3%)

Materials

Estimated
$1,419
Actual
$1,495
+$76 (+5.4%)

Labor

Estimated
$2,520
Actual
$2,730
+$210 (+8.3%)
Labor hours: 36.0 est / 39.0 act (+8.3%)100% tracked
ItemCategoryEstActualVariance
Hang+$187 (+12.3%)
5/8" Type X Drywall
Purchase · 2 extra sheets — cut waste
Materials$880
40 sheet
$924+5.0%+$44
1-5/8" Coarse Drywall Screws
Purchase
Materials$45
5 lb
$48+6.7%+$3
Construction Adhesive
Purchase
Materials$36
6 tube
$36On budget
Hang Labor
Time Tracking
Labor$560
8 hr
$700
10 hr
+25.0%+$140
Tape & Mud+$26 (+1.9%)
All-Purpose Joint Compound
Purchase · extra coat on ceilings
Materials$180
12 box
$210+16.7%+$30
Paper Joint Tape
Purchase
Materials$30
6 roll
$30On budget
Metal Corner Bead
Purchase
Materials$64
16 ea
$60-6.2%-$4
Tape & Mud Labor
Time Tracking
Labor$1,120
16 hr
$1,120
16 hr
On budget
Sand-$70 (-15.8%)
Sanding Screens (220)
Purchase
Materials$24
4 pack
$24On budget
Sand Labor
Time Tracking
Labor$420
6 hr
$350
5 hr
-16.7%-$70
Texture / Prime+$3 (+0.5%)
PVA Drywall Primer
Purchase · got it on sale
Materials$90
5 gal
$85-5.6%-$5
Wall Texture (Orange Peel)
Purchase
Materials$70
2 bag
$78+11.4%+$8
Texture / Prime Labor
Time Tracking
Labor$420
6 hr
$420
6 hr
On budget
Unaccounted Labor· not in estimate+$140 (+100.0%)
Punch-list / Cleanup
Time Tracking · not in original estimate
Labor$0
0 hr
$140
2 hr
+100.0%+$140

Cost actuals are for internal estimating accuracy only. They do not replace certified payroll, lien waivers, or jurisdiction-required documentation. Labor actuals pull from approved field time entries — verify overtime, hazloc premiums, and prevailing-wage classifications before using these figures for billing or payroll.

Line-Item Cost Tracker

Flat estimate-vs-actual tracker for ad-hoc cost items.

Estimated Total

$2,910

Actual Total

$2,515

Variance

$395
(-13.6%)

% Complete

78%

Cost Items

ItemCategoryEstimatedActualVarianceStatusActions
200A Main Panel
Eaton CH40B200
From Project
Materials$450$0$450
4/0 XHHW-2 Copper (100ft)
Southwire
From Project
Materials$280$295+$15
2" PVC Conduit (20ft)
Cantex Schedule 40
From Project
Materials$85$78$7
#12 THHN (500ft)
Copper, 90°C rated
From Project
Materials$125$135+$10
20A GFCI Breakers (4)
Eaton CHFGF120
From Project
Materials$180$0$180
Conduit Fittings
LB, couplings, adapters
From Project
Materials$65$72+$7
Electrical Installation Labor
18 hours @ $75/hr
Labor$1,200$1,350+$150
Electrical Permit
City permit fee
Permits$125$135+$10
Excavation Subcontractor
Trenching for service
Subcontractors$400$450+$50

Actions

Cost Breakdown

Estimated Total$2,910
Actual Total$2,515

By Category

Materials$580
Labor$1,350
Subcontractors$450
Permits$135

Project Info

Job Type:200A Service Upgrade
Location:Austin, TX
Start Date:7/9/2026
Items Tracked:9
From Project:6